Our team executed a significant thermal insulation project at the Sainsbury's Pineham site, focusing on efficiency and system protection.
Project Overview
The project involved insulating a complex array of pipework and vessels within an energy centre, both externally and internally, ensuring optimal thermal performance.

Project Challenges:
Insulating extensive and varied pipework, including complex configurations and sensitive valves, required precise application and bespoke solutions.
Project Solutions:
Enviroshield deployed a combination of rigid insulation, bespoke metal cladding, and custom-fabricated removable insulation jackets to meet all project demands.
Delivery Approach
Our methodical approach ensured precise installation and lasting performance across all aspects of the insulation works.

External Cladding
Applied durable metal cladding to external pipework and vessels for weather protection and thermal retention.
Plant Room Insulation
Insulated internal plant room pipework and equipment, including pumps and valves, to enhance operational efficiency.
Removable Jackets
Fabricated and installed custom removable insulation jackets for critical valves and flanges, facilitating easy maintenance.